8.7.1.3. Over Budget Bids


Definition

Over Budget Bids: Bids that exceed the available funding for the project.


Policy

Policy for over budget bids is to "Proceed in the best interests of Michigan Technological University considering implications of timing, need, cost, and funding source on the project's completion."


Procedure

The priority for dealing with over budget bids should be as follows:

  1. Negotiate with the lowest responsive bidder except as prohibited by Michigan law regarding contracts with corporations owned by University employees or trustees.


  2. Rebid with all responsive bidders via a post-bid addendum.


  3. Major redesign and rebid.


  4. Delay or cancel project.


  5. Seek additional funding (depending on the situation this may occur first, last, in combination with 1, 2, 3, or 4, or not at all.)

History
Adopted: 02/05/2001

Top of Page

PREVIOUS PAGE


Chapter Table of Contents  |  Table of Contents  |  Search  |  MTU Home

Last Revised: 08 January 2002 - activated Search Engine
http://www.admin.mtu.edu/admin/procman/ch8p12.htm
Copyright © 2001-2002. Michigan Technological University. All Rights Reserved.
Address questions to: policy@mtu.edu.