22.4.5. Computers


Definition

Aggregate Purchase Cost: The total of all costs that will be required during the first three years of the purchase of a computer system.


General Information

The Computer Advisory Committee (CAC) has developed guidelines to follow when purchasing computer hardware, software, or other information processing services when the value is more than $49,999.99. Refer to the CAC Library Web site http://www.it.mtu.edu/cac/, to review the computer acquisitions guidelines in their entirety.


Policy

Different information and approval reviews exist based upon the funding needed for the computer purchase. In the levels below, the aggregate purchase cost is defined as the total of all costs for the system that will be required during the first three years:

The information presented for the above reviews will include:


Procedure

To purchase a computer related item, do the following:

  1. Refer to the above review levels and determine the appropriate review.


  2. If the aggregate purchase does not require a review, complete a Purchase Requisition, either paper or a Banner requisition, and submit for appropriate approval. Refer to section 22.2.4. Purchase Requisitions for procedures on completing a requisition.


  3. If the aggregate purchase is $50,000 or more, send a memo describing the computer related equipment with specifications to the Acquisiton Subcommittee and request approval for purchase.


  4. Once approved by the Acquisiton Subcommitee and/or the CAC, complete the paper Purchase Requisition, and complete the 17.b. field by indicating the Subcommittee’s approval number for such purchases, or


  5. Complete a Banner requisition and forward a copy of the Acquisiton Subcomittee’s approval to the Purchasing Department.

    Refer to section 22.2.4. Purchase Requisitions for procedures on completing a requisition.
History
Adopted: 09/14/2001

Top of Page
PREVIOUS PAGE NEXT PAGE


Chapter Table of Contents  |  Table of Contents  |  Search  |  MTU Home

http://www.admin.mtu.edu/admin/procman/ch22/ch22p27.htm
Copyright © 2002. Michigan Technological University. All Rights Reserved.
Address questions to: policy@mtu.edu.